Logistics RFQ checklist for Afghanistan: what to specify before suppliers price

Quotations for the same assignment differ mostly because the request left something open: where the handover happens, who loads and inspects, which records come back, what the price includes. This checklist and template close those gaps before suppliers price.

A logistics request for quotation (RFQ) for work inside Afghanistan should let every supplier price exactly the same job. It needs eight things: the scope and where it ends, what moves and how much of it, every delivery and handover point to district level, the dates and the assumptions behind them, who packs, loads, stores, inspects and distributes, who approves and who may sign for the goods, the records that must come back, and the basis the price is quoted on. Leave any of them open and each supplier fills the gap with its own assumption. The quotations then look comparable and are not.

The checklist below follows that order, and the template at the end turns it into a form you can print, take into Word or adapt. It applies to transport, storage, kitting and distribution, alone or together. Buying the goods themselves is a procurement request of its own; the procurement planning guide covers specifications and quotation comparison for goods, and the vehicle-rental guide has its own RFQ for vehicles with drivers.

Start with the scope, and where it ends

The first paragraph of the request should say what the supplier is being asked to do and, just as plainly, what it is not. Most disputes about a logistics invoice are disputes about where the scope ended.

  • Services in the scope

    Road transport, storage, kitting or repacking, distribution to recipients, inspection, reporting, or a combination. Tick each one rather than describing the job in a sentence a supplier can read two ways.

  • Where the assignment starts

    A supplier's gate in Kabul, your own warehouse, a provincial store or the point where imported goods are released after customs. International freight and customs clearance are separate services, often from separate providers; name the handover point between them.

  • Where it ends

    Delivery to a district store, handover to a partner organisation at a site, or distribution to each household on a list. Each is a different price and a different set of records.

  • What stays with you

    Recipient lists, community engagement, approvals, security decisions and any supply you provide yourself. Say so, so nobody prices it twice or not at all.

What moves: items, units and quantities

Describe the load the way it will be counted at every handover. If the waybill counts cartons, the request should count cartons; a kit counted as one line in the RFQ and as its contents on the delivery note cannot be reconciled afterwards.

For each line give the item and its specification, the unit (kit, carton, bag, pallet, tonne), the quantity, and the gross weight and volume of one unit. Vehicle choice and price depend on weight and volume together: a truck full of blankets is full long before it is heavy. Add the packaging, whether goods arrive palletised, and anything that needs particular handling, such as fragile equipment or goods that must stay dry or upright. If quantities are estimates, say so and say by how much they may change.

Every place, to district level, with a handover point

"Delivery to Badakhshan" is not an address. Name the province, the district and the site, the organisation that receives the goods there, and the role of the person who may sign for them. A delivered price to a provincial centre is a different number from a delivered price to a district two days further on, and the difference is where a vague request costs most.

Say what you know about the last part of the route as well. The Logistics Cluster's road network assessment (opens in a new tab) records that many unpaved rural roads become impassable in heavy rain or winter, so a site that needs a smaller vehicle for the last kilometres, or a transfer from a truck, should be named as one. If you do not know, say that too and ask the supplier to state its assumption for each location.

Dates, milestones and the season

Give the earliest start, the delivery window for each location and any fixed date, such as a distribution day already announced to a community. Say whether each date is firm or a target. Then list the milestones that sit between award and delivery: sample or specification approval, inspection before dispatch, dispatch, delivery, and the date the closeout records are due.

A date is only as good as the access assumption behind it. State yours (roads open, no change of season, sites accessible on the planned day) and ask each supplier to state theirs, together with how and how quickly it will tell you when one fails. Winter changes the operation for high-altitude districts; the winter pre-positioning guide shows how to plan back from the last safe delivery date.

Who does what

Every task in the movement needs one owner. The quickest way to find the gaps is a responsibility table, filled in by you before the RFQ goes out:

TaskUsually decided by youWhat the supplier should confirm
Packing, kitting and labellingWho does it, to which compositionLabour, materials, labels and the count
Loading at originWho loads, and who witnessesLoading labour and the loading record
Inspection before dispatchWho inspects, to what standardAccess for the inspector, holding time
Storage before or after transportWhere, for how longSpace, conditions, stock records
Transport and routeDestinations, dates, restrictionsVehicles, routes, the waybill
Offloading and stacking at the destinationWho provides labour at the siteWhether offloading is in the price
Distribution to recipientsLists, verification rules, consentStaff, site set-up and the distribution list
Disposal of packaging or rejected goodsThe rule your donor appliesWho removes it, and at whose cost

A row nobody has claimed is a cost that will appear later, usually as a waiting-time charge or an offloading fee at the site.

Approvals and the authority to sign

Name who approves a sample or a specification, who accepts an inspection result, who releases goods from a store, and who may approve a change. At the destination, name the role (and, once known, the person) who may sign the delivery note, with the stamp they will use, and what the receiver does when the delivery is short or damaged: the shortfall is written on the document before anyone signs. Goods handed to whoever happens to be present are goods whose delivery cannot be proved.

The records the price must include

Records take staff time, and staff time is priced. List every record you need, the template it comes in and when it is due:

  • Waybill

    At dispatch, one per vehicle, with the goods by line, signed by the loader and the driver.

  • Goods received note

    When stock enters a store, against the waybill and the order.

  • Delivery note

    At every handover, signed by the authorised receiver, with any shortfall written on it.

  • Distribution list

    Where the supplier distributes to recipients, in your format, with each recipient's acknowledgement.

  • Inspection report and photographs

    Where you require them, and the rules on photographing people.

  • Progress and closeout reports

    How often, in which template and language, and the deadline for the closeout file after the last delivery.

The proof-of-delivery templates give a waybill, a goods received note and a delivery note you can attach to the request so every supplier quotes against the same paperwork.

Commercial terms: state yours, ask for theirs

The request should say what your organisation has decided and ask suppliers for the rest. Do not guess terms on a supplier's behalf; a quotation built on your guess is a quotation you will renegotiate.

  • Currency. The currency the quotation must be in, and whether one currency is required for all lines.
  • Price basis. Per trip, per tonne, per kit delivered, per pallet per month or per site, line by line, so quotations can be laid side by side.
  • Taxes. Ask each supplier to state which taxes its prices include and to show them on their own line, rather than assuming either way.
  • Payment terms. State your organisation's standard terms and the documents an invoice must carry. Ask each supplier to state any advance or other condition it requires, so it can be evaluated rather than discovered at contract.
  • Validity. How long the quotation must remain valid, long enough to cover your evaluation and approval.
  • Time-related charges. Waiting time at a site, storage beyond the agreed days, a return journey with undelivered goods: ask for the rate and the point at which it starts.

The Logistics Cluster's transport assessment (opens in a new tab) records that the authorities suspended insurance services in March 2022. Check the current position before relying on cover, and ask each supplier to state in its quotation who bears loss of and damage to goods in its custody.

Exclusions, assumptions and changes

Ask every supplier to list what its price excludes and what it assumes, in a section of its own. Then write down how a change works: who may request it, in writing to whom, how it is priced (from the rates in the quotation wherever possible), and that no changed work starts before written approval. The usual changes are worth naming in advance: a location added or dropped, quantities up or down, a date moved, a delivery cancelled after loading, and a site found inaccessible on the day.

How to compare the quotations

Bring every quotation to the same basis before comparing totals: the same quantities, the same delivery points, the same records, with exclusions added back where one supplier included what another left out. A delivered cost per unit for each location is often the clearest single comparison. Price is one criterion; state the others in the request with their weights, such as coverage of the locations named, the records offered, references for similar work and the time to replace a vehicle or a failed delivery.

Clarify in writing, and keep two kinds of clarification apart. A question about the request, before quotations are due, is answered in writing to every supplier, with the question but without saying who asked, and any change to the request goes to all of them at once. A question about one supplier's quotation, once quotations are in, goes to that supplier alone and stays on file: the answer may change neither the substance nor the price of the offer, and nothing learned from one supplier is passed to another. Both rules are in the UN's Procurement Practitioner's Handbook (opens in a new tab). Record the comparison, the recommendation and the approval in one note; it is the first document an audit of the award will ask for.

The template

Complete the request in this form and send it to every supplier the same way. Strike out any section that does not apply rather than deleting it, so suppliers see it was considered.

Template · blank, to print or edit

Request for quotation: logistics services in Afghanistan

Completed by the requesting organisation and sent to every supplier in the same form.

The request

Requesting organisation

ContactName, role, email and telephone

RFQ reference and date

Questions byDate, and the address to send them to; every answer goes to every supplier

Quotations dueDate, time and how to submit

Quotation valid for at least

Scope

  • Road transport
  • Storage before or after transport
  • Packing, kitting or labelling
  • Distribution to recipients
  • Inspection
  • Reporting and closeout file

The assignment starts atSite, store or release point

The assignment ends atStore, site handover or household

Not in the scopeWhat stays with the requesting organisation

Goods

LineItem and specificationUnitQuantityGross weight per unit (kg)Volume per unit (m³)PackagingSpecial handling

Quantities areFirm, or estimates that may change by up to …%

Locations and handover points

ProvinceDistrictSite or handover pointReceiving organisationWho may sign (role)Lines and quantitiesRequired byAccess notes

Dates and milestones

Earliest start

Sample or specification approval

Inspection before dispatch

Delivery windowsBy location; firm or target

Closeout records due

Access assumptionsYours; ask the supplier to state its own

Responsibilities

TaskRequesting organisationSupplierOtherNotes
Packing, kitting and labelling
Loading at origin
Inspection before dispatch
Storage
Transport
Offloading at destination
Distribution to recipients
Disposal of packaging or rejected goods

Approvals and acceptance

Approves samples and specifications

Accepts inspection results

Releases goods from storage

Approves changes

Signs for goods at each destinationRole, and the stamp used

Records and reporting

  • Waybill at dispatch, one per vehicle
  • Goods received note when stock enters a store
  • Signed delivery note at every handover
  • Distribution list with acknowledgements, in our format
  • Inspection report and photographs, under our rules
  • Progress reports, and a closeout file by the date above

Templates and languageAttach yours, or say the supplier's may be used

Commercial terms

Currency of the quotation

Our payment termsStated by the requesting organisation

Documents an invoice must carry

TaxesSupplier states which are included, on their own line

Advance or other condition requiredSupplier states, or none

Loss of or damage to goods in the supplier's custodySupplier states who bears it, and the insurance position

Price schedule (the supplier completes)

LineUnitQuantityRateTotalTaxes included?Notes
Transport, by route
Loading and offloading
Storage
Packing, kitting and labelling
Distribution, by site
Inspection support
Reporting and closeout file
Mobilisation, if charged
Waiting time, per day after …
Anything else charged

Exclusions, assumptions and changes (the supplier completes)

Excluded from the price

AssumedAccess, dates, quantities

Rates for changesAdded location, extra day, cancelled trip

Evaluation, stated in advance

CriterionWeight %Supplier ASupplier BSupplier C
Meets the scope and the records required (pass or fail)
Delivered cost, all lines on one basis
Coverage of the locations named
References for similar work
Records and reporting offered
Handling of delays and failed deliveries

Attach with the quotation

  • Business licence and tax identification number
  • Two references for similar work, with contacts
  • A sample of the records offered, with personal data removed
  • Who will do the work in each location named

Supplier's declaration

Supplier

Authorised signatory

Signature and date

Quotation valid until

An example, filled in

The lines below show how the goods and locations sections read once completed. The organisation, the quantities and the places are invented for illustration; this is not a real tender.

Invented example. 900 hygiene kits held in the requesting organisation's Kabul store, to be delivered to two district handover points and one provincial store, for distribution by a partner.

ProvinceDistrictHandover pointWho may signQuantityRequired byAccess notes
ParwanCharikarPartner's district storeStore manager, with stamp300 kits (60 cartons)Firm datePaved road
BamyanYakawlangCommunity centrePartner's field officer250 kits (50 cartons)Target dateLast 12 km unpaved; small truck
BamyanBamyan centrePartner's provincial storeStore manager, with stamp350 kits (70 cartons)Firm dateGoods received note on arrival

One unit is a carton of five kits: 21 kg and 0.11 m³ gross. Loading in Kabul is the requesting organisation's; offloading and stacking at each site are the supplier's.

When Zhikal answers an RFQ

Zhikal prices transport, storage, kitting, distribution and the records that go with them, alone or as one project logistics assignment, with road transport, warehousing and procurement as separate services where you need only one. Each stage of its delivery model leaves a named record: a scope note and workplan, a resource assignment, bid analysis and inspection reports, waybills and a field supervision log, the evidence file, and a closeout report. Disruptions to access or supply are reported to the client within 24 hours with a proposed alternative.

Two projects show the records in practice: a five-province food supply with delivery evidence captured at every drop point, and a nationwide non-food-item retainer whose task orders each run through the same controls. To have a requirement priced, send the completed RFQ, or your own, to the team in Kabul. If the requirement is still taking shape, the goods, the locations, the dates and the records you need are enough to start the conversation.

Sources

External sources are cited for the facts they report and were checked when this guide was last updated. Citing them implies no relationship with, or endorsement by, their publishers.

Related services.

Who this is written for.

From the record.

An assignment of the same kind, as the corporate profile records it.

Case 02 · ASSDO · 2021–22

Warehouse management

A 12-month, audit-ready assignment spanning ten provinces, including delivery, packaging, records and warranty obligations.

10 provinces · 10 provinces

Further reading.